Currently when you run this report by completion date of project, it does not actually removed those projects that are completed after the date selected despite there being a request for date range. Is there any way for the report to exclude certain completed jobs if it is out of date range?
0 Votes
1 Comments
H
Henrik Burmanposted
9 months ago
Admin
Hi Mackenzie,
The Projects Completed in Period report will run off of the date a project was marked as completed in WorkGuru. I ran a test of this report against your tenancy using a month timeframe and any project being listed in the report was completed in that month. If you are still having issues I would suggest submitting a ticket with more context/images to support@workguru.io and we can look into it further for you.
Currently when you run this report by completion date of project, it does not actually removed those projects that are completed after the date selected despite there being a request for date range. Is there any way for the report to exclude certain completed jobs if it is out of date range?
0 Votes
1 Comments
Henrik Burman posted 9 months ago Admin
Hi Mackenzie,
The Projects Completed in Period report will run off of the date a project was marked as completed in WorkGuru. I ran a test of this report against your tenancy using a month timeframe and any project being listed in the report was completed in that month. If you are still having issues I would suggest submitting a ticket with more context/images to support@workguru.io and we can look into it further for you.
Best regards,
Henrik
0 Votes