MCP updates

Posted 2 days ago by Jeff McDowell

Post a topic
J
Jeff McDowell

We use the WorkGuru connector with Claude to set up jobs, and we're now building routing-based production scheduling on top of it. Each job gets an ordered set of operations (e.g. Manual Machining > Fabrication > Borer > Paint > Assembly) as task lines with forecast hours, grouped by project phase. Our staff book time to these lines in the phone app, and that part works well.
We want every rate and cost to come from the WorkGuru Tasks list, not from anything we keep outside WorkGuru. Testing on job J013561, we found four gaps in the connector:
  1. Read the Tasks list. There's no tool to list labour tasks. search_catalogue only returns products, and "General Engineering" returns nothing. Could you add list_tasks / get_task, returning task id, name, cost rate, sell rate, tax code, billable default and active flag?
  1. Add task lines from the Tasks list (most important). add_project_task needs us to supply unitPrice and unitCost, and the line isn't linked to a catalogue task. Could it accept a taskId so the server fills in the name, sell rate, cost, tax and billable from the Tasks list, the same as adding a task in the project editor? Price and cost could stay as optional overrides.
  1. Create phases. add_project_task and update_project_task only accept phases that already exist on the job, and there's no tool to create one. Could you add create_project_phase, or an option to create the phase if it's missing?
  1. Hours booked per task line. get_project_tasks doesn't return hours booked per line. Adding hoursBooked (and ideally hoursApproved) would let us show the hours remaining on each operation.
These would also help:
  • Setting start and end dates on task lines
  • A sort order for task lines
  • Editing the project name and description through update_project