A client credit note reverses retention when it has a line on your retention product, on a credit note linked to the project. WorkGuru reads the line's sign: a negative line reverses retention that was held, and a positive line reverses a release you claimed.

Reverse a Retention Held

Credit a progress claim that held retention:

  1. Create an adhoc client credit note linked to the project.
  2. Add the lines you're crediting. 
  3. Add a line on your retention product with the retention amount as a negative value, for example −500.00 to reverse $500 held. 
  4. Save and Approve the credit note.

The project's Held to date drops by that amount once the credit note is approved.

Reverse a Retention Claim

Credit a release invoice, for example one claimed twice by mistake:

  1. Create an adhoc client credit note linked to the project.
  2. Add a line on your retention product with the released amount as a positive figure.
  3. Save and Approve the credit note.

The project's Claimed figure drops by that amount, and the retention is outstanding again.


Note:

  • A credit note that would leave more retention released than held is refused when you save, approve or delete it. The message names the project and the amounts.
  • Discounts and surcharges on a credit note are never worked out on the retention line.
  • A credit note with no project, or with no line on the retention product, doesn't affect retention.
  • Credit notes appear in the project's Retention by claim ledger.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article