Retention schemes let you create repeatable templated retention schemes that can be selected on the relevant projects.  You can also create a retention scheme per project without creating pre-set schemes if required. To create a retention scheme once the retentions settings are saved, open the Retention settings in the Invoice tab of the settings page (Administration -> Settings -> Invoices) and click Manage Retention Schemes.

From the retention scheme dashboard, click New Scheme

Complete the New Retention Scheme popup to add a new scheme:

  • Name - Retention name (may be specific to a project etc)
  • Cap (% of contract value) - When the scheme is copied onto a project, WorkGuru turns this into a dollar cap from the project's value (Optional)
  • Retention Bands - Click Add Band for each band:
    • Claimed value from - The claimed amount this band starts at. The first band starts at 0.
    • Retention % - The percentage held on claims in this band.
  • Release Schedule - Click Add Release for each release.  Note: The release shares should add up to 100%. WorkGuru warns you if they don't, and refuses a schedule that adds up to more than 100%. Shares like 33.33% three times will round up and count as 100%
    • Name - For example Practical completion or End of defects period.
    • When - On practical completion, Months after practical completion, or Fixed date.
    • Date or months - The date for a fixed-date release, or the number of months for a months-after release.
    • Share % - The share of held retention released at this point.

Click Save when complete.

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article