Report Field Definitions - Projects/Project Groups/Recurring Projects/Production Jobs

Modified on Mon, 3 Nov at 3:19 PM

When it comes to keeping track of projects in WorkGuru, there’s a stack of reports ready to help you stay on top of the important stuff. Think of this section like your local bartender giving you the run-down on what’s on tap tonight — you might not need every pint on the menu, but knowing what’s there can save you from some headaches later.

These reports cover everything from what projects are coming due, to how much money you’ve actually made, to those tricky “what was quoted vs what actually happened” questions. Some are quick one-liners, others go deep with pivot tables and all the trimmings. The idea here isn’t to drown you in jargon — it’s to give you a plain-English guide so you can use the right report at the right time.


PROJECT REPORTS



Current Projects Due In Period

Overview
This report shows only projects due for completion within the selected date range. Handy if you just want a straight-up answer to “what do we need to finish this week/month/quarter?” without wading through all the other project noise.

Fields

FieldNotes / Expected ValuesDescription
ACTUALHOURShour/minutesproject total timesheet length
ASSETtextproject asset
BILLINGCLIENTtextbilling client name
CLIENTtextclient name
CLIENTPURCHASEORDERtexttransaction 'client PO'
CREATIONDATEDD/MM/YYYYproject creation date
DATEDD/MM/YYYYproject start date
DAYnumerical valueproject start day
DAYOFWEEKtextday name
DESCRIPTIONtextproject description
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueproject forecast cost
FORECASTTIMEhour/minutesproject forecast time
FORMATSTARTDATEYYYY/MM/DDproject format start date
InvoicedBaseCurrency 
dollar value
total project invoiced amount in base currency
ISOSTARTDATEYYYY/MM/DDproject ISO start date
MONTHnumerical month/month name abbreviatedproject start month
PROJECTGROUPtext
project group name
PROJECTGROUPDESCRIPTIONtextproject group description
PROJECTMANAGERtextproject manager
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valueactual purchase costs
QTRmonth-month abbreviatedfinancial year quarter
QUOTEnumericalquote number
QUOTEDATEDD/MM/YYYYQuote date
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
TOTALdollar valueproject base currency total
(total * exchange rate)
TOTALINVOICEDdollar valuetotal project invoiced amount
YEARnumerical valueproject start year
DOLLARPROFITdollar valueproject profit

Projects Completed In Period

Overview
This report is all about wrapping things up — it lists projects that hit the finish line during your chosen date range. Great for checking what’s actually been delivered and closed off, rather than just what’s floating around half-done.

Fields

FieldNotes / Expected ValuesDescription
ACTUALHOURShour/minutesproject actual hours
ASSETtextproject asset
BILLINGCLIENTtextproject billing client
CLIENTtextproject client
CLIENTPURCHASEORDERtextproject 'Client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CREATIONDATEDD/MM/YYYYproject creation date
DATEYYYY/MM/DDproject creation date
DAYnumerical valueproject creation day
DAYOFWEEKtextproject creation day name
DESCRIPTIONtextproject description
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueproject forecast cost
FORECASTTIMEhour/minutesproject forecast time
FORMATSTARTDATEYYYY/MM/DDproject format start date
InvoicedBaseCurrency 
dollar value
total project invoiced amount in base currency
ISOCOMPLETEDDATEYYYY/MM/DDproject ISO completed date
ISOSTARTDATEYYYY/MM/DD
project ISO start date
MONTHnumerical month/month name abbreviatedproject start month
PROJECTGROUPtextproject group name
PROJECTGROUPDESCRIPTIONtextproject group description
PROJECTMANAGERtextproject manager
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valueproject purchase cost
QTRmonth-month abbreviatedfinancial year quarter
QUOTEnumericalquote number
QUOTEDATEDD/MM/YYYY
Quote date
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUScancelled/completedproject status
TOTALdollar valueproject base currency total
(total x exchange rate)
TOTALINVOICEDdollar valueproject total invoiced
YEARnumerical valueproject start year
DOLLARPROFITdollar valueproject profit

All Projects Summary Report

Overview
A big-picture look at every project in the system, regardless of whether they’re open, closed, overdue, or still waiting to start. Use this one when you want a high-level snapshot of the whole workload.

Fields

FieldNotes / Expected ValuesDescription
ACTUALHOURShour/minutesproject actual hours
BILLINGCLIENTtextproject billing client
CLIENTtextproject client
CLIENTPURCHASEORDERtextproject 'client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CREATIONDATEDD/MM/YYYYproject creation date
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueproject forecast cost
FORECASTTIMEhour/minutesproject forecast time
FORMATSTARTDATEYYYY/MM/DDproject format start date
InvoicedBaseCurrency 
dollar value
total project invoiced amount in base currency
MONTHnumerical month/month name abbreviatedproject start month
PROJECTGROUPtextproject group name
PROJECTGROUPDESCRIPTIONtextproject group description
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valueproject purchases cost
QUOTEnumerical valuequote number
QUOTEDATEDD/MM/YYYYQuote Date
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
TOTALdollar valueproject base currency total
(total x exchange rate)
TOTALINVOICEDdollar valueproject total 
YEARnumerical valueproject start year
DOLLARPROFITdollar valueproject profit

Quoted Projects Summary Report

Overview
This one’s about what’s been quoted, not necessarily what’s been started. It helps you track all projects that have made it to the quoting stage, giving you a view of your pipeline before jobs actually kick off.

Fields

FieldNotes / Expected ValuesDescription
ACTUALHOURShour/minutesproject actual hours
BILLINGCLIENTtextproject billing client
CLIENTtextproject client
CLIENTPURCHASEORDERtext project 'client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CREATIONDATEDD/MM/YYYYproject creation date
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueproject forecast cost
FORECASTTIMEhour/minutesproject forecast time
FORMATSTARTDATEYYYY/MM/DDproject format start date
InvoicedBaseCurrency 
dollar value
total project invoiced amount in base currency
MONTHnumerical month/month name abbreviatedproject start month
PROJECTGROUPtextproject group name
PROJECTGROUPDESCRIPTIONtextproject group description
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valueproject purchases cost
QUOTEnumerical valuequote number
QUOTEDATEDD/MM/YYYYquote date
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
TOTALdollar valueproject base currency total
(total x exchange rate)
TOTALINVOICEDdollar valueproject total invoiced
YEARnumerical valueproject start year
DOLLARPROFITdollar valueproject profit

Project Value vs Invoiced Report by Start Date 

Overview
This compares what a project was supposed to be worth (its value) against what’s actually been invoiced, broken down by start date. Great for spotting gaps between “what we thought we’d earn” and “what we actually billed.”

Fields

FieldNotes / Expected ValuesDescription
CLIENTtextproject client
CLIENTPURCHASEORDERtextproject 'client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CREATIONDATEDD/MM/YYYYproject creation date
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject creation day
DAYOFWEEKtextproject creation day name
FORECASTVALUEdollar valueproject forecast value
INVOICEDVALUE
dollar valueproject invoiced value
MONTHnumerical month/month name abbreviatedproject start month
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTnumerical valueproject number
STATUStextproject status
QTRmonth-month abbreviatedfinancial year quarter
YEARnumerical valueproject start year

Profit by Project

Overview
This report is based on projects with start and due dates between the selected date range, focusing on completed projects within that period. Useful for getting a clear picture of profit per project and spotting any that over- or under-performed financially.

Fields

FieldNotes / Expected ValuesDescription
CLIENTtextproject client
CLIENTCREDITSdollar valueproject client total credit value
CLIENTPOtextproject 'client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CONTACTtextproject client contact
DATEYYYY/MM/DDproject format start date
DAYnumerical valueproject creation day
DAYOFWEEKday nameproject creation day name
DESCRIPTIONproject description fieldproject description
DOLLARPROFITdollar valueproject total profit
DUEDATEDD/MM/YYYYproject due date
MONTHnumerical month/month name abbreviatedproject start month
PERCENTAGEPROFITpercentageproject profit percentage
PRODUCTANDPURCHASETOTALdollar valuetotal actual cost value of products and purchases
PRODUCTCOSTdollar valueproject total product cost
PRODUCTFORECASTCOSTdollar valueproduct total forecast cost
PRODUCTFORECASTREVENUEdollar valueproduct total forecast revenue
PRODUCTREVENUEdollar valueproduct total actual revenue
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valuepurchase total actual cost
PURCHASEFORECASTCOSTdollar valuepurchase total forecast cost
PURCHASESFORECASTREVENUEdollar valuepurchase total forecast revenue
PURCHASESREVENUEdollar valuepurchase total revenue
QTRmonth-month abbreviatedfinancial year quarter
QUOTEACCEPTEDDATEDD/MM/YYYYquote accepted date
QUOTENUMBERnumerical valuequote number
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
SUPPLIERCREDITSdollar valueproject supplier total credit value
TASKACTUALQTYhour/minutestask total actual quantity
TASKCOSTdollar valuetask total cost
TASKFORECASTCOSTdollar valuetask total forecast cost
TASKFORECASTQTYhour/minutestask total forecast quantity
TASKFORECASTREVENUEdollar valuetask total forecast revenue 
TASKREVENUEdollar valuetask total revenue
TOTALCOSTdollar valueproject total cost
TOTALFORECASTCOSTdollar valueproject total forecast cost
TOTALFORECASTREVENUEdollar valueproject total forecast revenue
TOTALREVENUEdollar valueproject total revenue
YEARnumerical valueproject start year

Profit by Project Within Period

Overview
This report covers projects with any activity at all between the selected date range. It allows filtering to include only received/invoiced POs in costing if desired. Good for more dynamic reporting beyond just completed projects.

Fields

FieldNotes / Expected ValuesDescription
CLIENTclient name fieldproject client
CLIENTCREDITSdollar valueproject client total credit value
CLIENTPOtextproject 'client PO'
COMPLETEDDATEDD/MM/YYYYproject completed date
CONTACTtextproject client contact
DESCRIPTIONtextproject description
DOLLARPROFITdollar valueproject total profit
DUEDATEDD/MM/YYYYproject due date
ESTIMATEDBILLINGdollar valuetotal forecast sum minus total forecast revenue, rounded to 2 decimals
PERCENTAGEPROFITpercentageproject profit percentage
PRODUCTANDPURCHASETOTALdollar valuetotal actual cost value of products and purchases
PRODUCTCOSTdollar valueproject total product cost
PRODUCTFORECASTCOSTdollar valueproduct total forecast cost
PRODUCTFORECASTREVENUEdollar valueproduct total forecast revenue
PRODUCTREVENUEdollar valueproduct total actual revenue
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PURCHASECOSTdollar valuepurchase total actual cost
PURCHASEFORECASTCOSTdollar valuepurchase total forecast cost
PURCHASESFORECASTREVENUEdollar valuepurchase total forecast revenue
PURCHASESREVENUEdollar valuepurchase total revenue
QUOTEACCEPTEDDATEDD/MM/YYYYquote accepted date
QUOTENUMBERnumerical valuequote number
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
SUPPLIERCREDITSnumerical value project supplier total credit value
TASKACTUALQTYhour/minutestask total actual quantity
TASKCOSTdollar valuetask total cost
TASKFORECASTCOSTdollar valuetask total forecast cost
TASKFORECASTQTYhour/minutestask total forecast quantity
TASKFORECASTREVENUEdollar valuetask total forecast revenue 
TASKREVENUEdollar valuetask total revenue
TOTALCOSTdollar valueproject total cost
TOTALFORECASTCOSTdollar valueproject total forecast cost
TOTALFORECASTREVENUEdollar valueproject total forecast revenue
TOTALREVENUEdollar valueproject total revenue
YEARnumerical valueproject start year

Project Task Lines by Start Date Pivot Report

Overview
This pivot table report brings all task lines associated with projects that started between your filter dates into a pivot grid. Perfect for dissecting actual task-level effort and cost.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valuetask total actual cost
ACTUALHOURShour/minutestask total actual hours
ASSETtextproject asset
BILLABLEyes/no
task billable status
BILLINGCLIENTADDRESS1textbilling client address line 1
BILLINGCLIENTADDRESS2textbilling client address line 2
BILLINGCLIENTCITYtextbilling client city
BILLINGCLIENTPOSTCODEtextbilling client post code
BILLINGCLIENTSTATEtextbilling client state
BILLINGCLIENTSUBURBtextbilling client suburb
CLIENTtextclient name
CLIENTADDRESS1textproject client address 1
CLIENTADDRESS2textproject client address 2
CLIENTCITYtextproject client city
CLIENTCONTACTtextproject client contact name
CLIENTEMAILtextproject client email
CLIENTPOSTCODEtextproject client postcode
CLIENTPURCHASEORDERtextproject 'client PO'
CLIENTSTATEtextproject client state
CLIENTSUBURBtextproject client suburb
CODEtextproject client code
COMPLETEDDATEDD/MM/YYYYtask completed date
COSTMULTIPLIERnumerical valuetask cost multiplier
DESCRIPTIONtexttask description
DUEDATEDD/MM/YYYYproject due date
FINISHTIMEYYYY/MM/DDtask finish date
FORCETASKRATECOSTINGdollar valuetask forecast rate cost
FORECASTCOSTdollar valuetask total forecast cost
FORECASTHOURShour/minutestask total forecast hours
FORECASTVALUEdollar valuetask total forecast value
FREQUENCYnumber of daysrecurring project frequency
InvoicedBaseCurrency 
dollar valuetotal project invoiced amount in base currency
INVOICEDHOURShour/minutestask timesheet invoiced hours
LASTINVOICEDATEDD/MM/YYYYproject last invoice date
LASTINVOICENOnumerical valueproject last invoice number
LASTPROJECTINVOICEDATEDD/MM/YYYYlast project invoice date
LASTPROJECTINVOICENOnumerical valuelast project invoice number
PHASEtexttask phase
PROFITdollar valuetask profit
PROJECTproject number - project nameproject number - project name
PROJECTGROUPtextproject group
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
REMAININGHOURShour/minutestask remaining hours (forecast task quantity minus actual timesheet hours quantity)
SELLPRICEdollar valuetask sell rate
STAFFtextstaff assigned to task
STARTDATEDD/MM/YYYYproject start date
STARTTIMEyear/month/day and time days:hours:minutesproject start time
STATUStexttask status
TASKtexttask name
TASKDUEDATEDD/MM/YYYYtask due date
TASKDUEDATEISOYYYY/MM/DDtask ISO due date
TASKSTARTDATEDD/MM/YYYYtask start date
TASKSTARTDATEISOYYYY/MM/DDtask ISO start date
TASKSTATUStexttask status
TAXNAMEtexttask tax name
TAXRATEpercentagetask tax rate
TAXTYPEtexttask tax type
TEAMStexttask teams
TOTALINVOICEDdollar valuetask total invoiced timesheets

Project Product Lines by Start Date Pivot Report

Overview
This pivot table report brings all product lines associated with projects starting between your provided filter dates into a pivot grid. It tracks forecast vs actual quantities and costs.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valueproduct total actual cost 
ACTUALQUANTITYnumerical valueproduct actual quantity
CLIENTtextproject client name
CLIENTADDRESS1textclient address line 1
CLIENTCITYtextclient address line 2
CLIENTEMAILtextclient email
CLIENTPOtexttransaction 'client PO'
CLIENTSUBURBtextclient suburb
DESCRIPTIONtextline description
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueproduct forecast cost
FORECASTQUANTITYnumerical valueproduct forecast quantity
INVOICEDAMOUNTdollar valueproduct invoiced amount
INVOICEDQUANTITYnumerical valueproduct invoiced quantity
PHASEtextproduct phase
PRODUCTNAMEtextproduct name
PROJECTproject number - project nameproject number - project name
PROJECTGROUPproject group name fieldproject group
PROJECTMANAGERproject manager name fieldproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PROJECTSTATUStextproject status
PURCHASECOSTdollar valuepurchase order product cost
PURCHASEQUANTITYnumerical valuepurchase order product quantity
SELLPRICEdollar valueproduct sell price
SKUtextproduct SKU
STARTDATEDD/MM/YYYYproject start date
STOCKUSAGECOSTdollar valuestock usage cost
STOCKUSAGEQUANTITYnumerical valuestock usage quantity
SUPPLIERtextsupplier name
TAXNAMEtexttax name
TAXRATEpercentagetax rate
TAXTYPEtexttax type
TRACKINGTYPENonstock, FIFO, Batch, Serialproduct tracking type

Project Task Lines by Start Date Pivot Report (Current Tasks) 

Overview
This pivot table report shows all task lines for projects that started within your filter dates. It’s like the previous task lines report, but only includes current, ongoing tasks.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valuetask total actual cost 
ACTUALHOURShours/minutestask total actual hours
ASSETtextproject asset
BILLABLEyes/no
task billable status
BILLINGCLIENTADDRESS1textbilling client address line 1
BILLINGCLIENTADDRESS2textbilling client address line 2
BILLINGCLIENTCITYtextbilling client city
BILLINGCLIENTPOSTCODEtextbilling client postcode
BILLINGCLIENTSTATEtextbilling client state
BILLINGCLIENTSUBURBtextbilling client suburb
CLIENTtextclient name
CLIENTADDRESS1textproject client address line 1
CLIENTADDRESS2textproject client address line 2
CLIENTCITYtextproject client city
CLIENTCONTACTtextproject client contact name
CLIENTEMAILtextproject client email
CLIENTPOSTCODEtextproject client postcode
CLIENTPURCHASEORDERtexttransaction 'client PO'
CLIENTSTATEtextproject client state
CLIENTSUBURBtextproject client suburb
CODEtextproject client code
COMPLETEDDATEDD/MM/YYYYtask completed date
COSTMULTIPLIERnumerical valuetask cost multiplier
DESCRIPTIONtexttask description
DUEDATEDD/MM/YYYYtask due date
FINISHTIMEYYYY/MM/DDtask finish date
FORCETASKRATECOSTINGtrue/falseis task rate forced on timesheet costs
FORECASTCOSTdollar valuetask forecast cost
FORECASTHOURShour/minutestask forecast hours
FORECASTVALUEdollar valuetask forecast value
FREQUENCYnumber of daysrecurring project frequency
InvoicedBaseCurrency dollar value task total invoiced timesheets in base currency
INVOICEDHOURShour/minutesinvoiced task timesheet hours
LASTINVOICEDATEDD/MM/YYYYlast invoice date for task line
LASTINVOICENOnumerical valuelast invoice number for task line
LASTPROJECTINVOICEDATEDD/MM/YYYYlast invoice date for project
LASTPROJECTINVOICENOnumerical valuelast invoice number for project
PHASEtexttask phase
PROFITtexttask profit
PROJECTproject number - project nameproject number - project name
PROJECTGROUPproject group name fieldproject group
PROJECTMANAGERproject manager name fieldproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
REMAININGHOURShour/minutestask remaining hours (forecast task quantity minus actual timesheet hours quantity)
SELLPRICEdollar valuetask sell price
STAFFtexttask staff name
STARTDATEDD/MM/YYYYproject start date
STARTTIMEYYYY/MM/DDproject start date
STATUStextproject status
TASKtexttask name
TASKDUEDATEDD/MM/YYYYtask due date
TASKDUEDATEISOYYYY/MM/DDtask due date
TASKSTARTDATEDD/MM/YYYYtask start date
TASKSTARTDATEISOYYYY/MM/DDtask start date
TASKSTATUStexttask status
TAXNAMEtexttask tax name
TAXRATEpercentagetask tax rate
TAXTYPEtexttask tax type
TEAMStexttask teams name
TOTALINVOICEDdollar valuetask total invoiced amount

Project Task Lines by Due Date Pivot Report

Overview
This pivot table report shows all task lines for projects due to finish within your filter dates. Handy for seeing what’s coming due soon and what resources are still required.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valuetask total actual cost

ACTUALHOURS


hour/minutestask total actual hours
ASSETproject asset fieldproject asset
BILLABLEyes/no
task billable status
BILLINGCLIENTADDRESS1textbilling client address line 1
BILLINGCLIENTADDRESS2textbilling client address line 2
BILLINGCLIENTCITYtextbilling client city
BILLINGCLIENTPOSTCODEtextbilling client postcode
BILLINGCLIENTSTATEtextbilling client state
BILLINGCLIENTSUBURBtextbilling client suburb
CLIENTtextclient name
CLIENTADDRESS1textproject client address line 1
CLIENTADDRESS2textproject client address line 2
CLIENTCITYtextproject client city
CLIENTCONTACTtextproject client contact name
CLIENTEMAILtextproject client email
CLIENTPOSTCODEtextproject client postcode
CLIENTPURCHASEORDERtransaction 'client PO' fieldtransaction 'client PO'
CLIENTSTATEtextproject client state
CLIENTSUBURBtextproject client suburb
CODEtextproject client code
COMPLETEDDATEDD/MM/YYYYtask completed date
COSTMULTIPLIERnumerical valuetask cost multiplier
DESCRIPTIONtexttask description
DUEDATEDD/MM/YYYYtask due date
FINISHTIMEYYYY/MM/DDtask finish date
FORCETASKRATECOSTINGdollar valueis task rate forced on timesheet costs
FORECASTCOSTdollar valuetask forecast cost
FORECASTHOURShour/minutestask forecast hours
FORECASTVALUEdollar valuetask forecast value
FREQUENCYnumber of daysrecurring project frequency
INVOICEDBASECURRENCYdollar valuetotal project task invoiced amount in base currency
INVOICEDHOURShour/minutesinvoiced task timesheet hours
LASTINVOICEDATEDD/MM/YYYYlast invoice date for task line
LASTINVOICENOnumerical valuelast invoice number for task line
LASTPROJECTINVOICEDATEDD/MM/YYYYlast invoice date for project
LASTPROJECTINVOICENOnumerical valuelast invoice number for project
PHASEtexttask phase
PROFITdollar valuetask profit
PROJECTproject number - project nameproject number - project name
PROJECTGROUPproject group name fieldproject group
PROJECTMANAGERproject manager name fieldproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
REMAININGHOURShour/minutestask remaining hours (forecast task quantity minus actual timesheet hours quantity)
SELLPRICEdollar valuetask sell price
STAFFtexttask staff name
STARTDATEDD/MM/YYYYtask start date
STARTTIMEYYYY/MM/DDtask start date
STATUStextproject status
TASKtexttask name
TASKDUEDATEDD/MM/YYYYtask due date
TASKDUEDATEISOYYYY/MM/DDtask due date
TASKSTARTDATEDD/MM/YYYYtask start date
TASKSTARTDATEISOYYYY/MM/DDtask start date
TASKSTATUStexttask status
TAXNAMEtexttask tax name
TAXRATEpercentagetask tax rate
TAXTYPEtexttask tax type
TEAMStexttask teams name
TOTALINVOICEDdollar valuetask total invoiced amount

WIP Actuals

Overview
WIP (Work in Progress) Actuals focuses on actual billed and costed elements of projects. Filters can include only received or invoiced POs. Perfect for financial tracking of ongoing projects.

Fields

FieldNotes / Expected ValuesDescription
BILLABLEPRODUCTTOTALdollar valueproducts total actual billable value
BILLABLEPURCHASESTOTALdollar valuepurchases total actual billable value
BILLABLETASKTOTALdollar valuetasks total actual billable value
CLIENTtextproject client name
CLIENTCREDITTOTALdollar valueclient total project credit value
CLIENTPURCHASEORDERtexttransaction 'client PO'
DESCRIPTIONtextproject description
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueforecast total cost
FORECASTREVENUEdollar valueforecast total revenue
FORECASTTIMEhour/minutesforecast total time
INVOICEDPRODUCTTOTALdollar valueproducts total invoiced value
INVOICEDPURCHASESTOTALdollar valuepurchases total invoiced value
INVOICEDTASKTOTALdollar valuetask total invoiced value
LASTINVOICEDATEDD/MM/YYYYproject last invoice date
LASTINVOICENOnumerical valueproject last invoice number
PRODUCTCOSTTOTALdollar valueproduct total actual cost
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PROJECTSTATUStextproject status
PURCHASECOSTTOTALdollar valuepurchase actual total cost
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
SUPPLIERCREDITTOTALdollar valuesupplier project credit total value
TASKCOSTTOTALdollar valuetask total cost
TOTALBILLABLEdollar valuetotal billable actual value
TOTALCOSTdollar valuetotal actual cost 
TOTALINVOICEDdollar valuetotal invoiced value
TOTALTIMEhour/minutestotal timesheet quantity
WIPVALUEdollar valuetotal WIP (billable actualsnot invoiced)

WIP Quoted

Overview
This report shows WIP but from a quoted perspective — it tracks the forecasted cost/revenue and what has been quoted, rather than actuals. Helps predict profitability before work is done.

Fields

FieldNotes / Expected ValuesDescription
BILLABLEPRODUCTTOTALdollar valueproduct total quoted billable value
BILLABLEPURCHASESTOTALdollar valuepurchase total quoted billable value
BILLABLETASKTOTALdollar valuetask total quoted billable value
CLIENTclient nameproject client
CLIENTCREDITTOTALdollar valueproject client credit total value
CLIENTPURCHASEORDERtexttransaction 'client PO'
DESCRIPTIONtextproject description
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueforecast total cost
FORECASTREVENUEdollar valueforecast total revenue 
FORECASTTIMEhour/minutesforecast total time
INVOICEDPRODUCTTOTALdollar valueproducts total invoiced value
INVOICEDPURCHASESTOTALdollar valuepurchase total invoiced value
INVOICEDTASKTOTALdollar valuetask total invoiced value
LASTINVOICEDATEDD/MM/YYYYproject last invoice date
LASTINVOICENOnumerical valueproject last invoice number
PRODUCTCOSTTOTALdollar valueproduct total actual cost
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PROJECTSTATUStextproject status
PURCHASECOSTTOTALdollar valuepurchase actual total cost
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
STARTDATEDD/MM/YYYYproject start date
SUPPLIERCREDITTOTALdollar valuesupplier project credit total value
TASKCOSTTOTALdollar valuetask total cost
TOTALBILLABLEdollar valuetotal billable quoted value
TOTALCOSTdollar valuetotal actual cost
TOTALINVOICEDdollar valuetotal invoiced value
TOTALTIMEhour/minutestotal actual timesheet quantity
WIPVALUEdollar valuetotal WIP (billable quoted value not invoiced)

Revenue Forecast by Quoted and Scheduled

Overview
This report generates a revenue recognition forecast based on the scheduled dates and quoted value of projects within the selected date range. Useful for anticipating income based on both current and upcoming projects.

Fields

FieldNotes / Expected ValuesDescription
AMOUNTdollar valueproject line item value
CLIENTtextclient
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject due day
DAYOFWEEKtextproject due day name
MONTHnumerical month/month nameproject due month number and month name
NAMEtextproject line item name
PROJECTtextproject number - project name
QTRmonth-monthproject due quarter
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
YEARnumerical valueproject due year

Project Progress Summary

Overview
This report summarises forecast and invoiced amounts per line item for a selected project, or all projects based on the selected end date or date range. It’s helpful for a quick view of project performance and completion status.

Fields

FieldNotes / Expected ValuesDescription
ACTUALWIPREMAININGdollar valueremaining WIP total based on actuals not invoiced
AMOUNTINVOICEDdollar valuetotal invoiced value
AMOUNTREMAININGdollar valuetotal outstanding value
BASEAMOUNTINVOICEDdollar valuetotal forecast amount minus the total invoiced amount
CLIENTtext
project client name
CONTACTtextproject client contact name
COSTdollar valueline item total cost
DESCRIPTIONtextline item description
FORECASTAMOUNTdollar valueforecast line item value
LINETYPEtextline item type (product, task)
NAMEtextline item name
PERCENTINVOICEDpercentageline item invoiced percentage
PERCENTREMAININGpercentageline item percentage left to invoice
PHASEtextline item phase
PRODUCTCATEGORYtextline item product category
PROJECTCOMPLETEDATEDD/MM/YYYYproject completed date
PROJECTDESCRIPTIONtextproject description
PROJECTDUEDATEDD/MM/YYYYproject due date
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PROJECTSTARTDATEDD/MM/YYYYproject start date
PROJECTSTATUStextproject status
PURCHASEORDERnumerical valuetransaction 'client PO'
QUOTENUMBERnumerical valuequote number
SKUtextline item SKU (products only)
SUPPLIERtextproduct details page supplier name
TOTALACTUALBILLABLEdollar valuetotal actual billable value

Project Forecast VS Actual

Overview
This report details forecast vs actual information for projects completed or due for completion within the selected period. Each line represents either a forecast or actual for the project. This report is a bit more complex in the logic used to provide some of the field values so it has been broken down in the description accordingly.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valueline item actual cost
task lines - expected value is always 0
timesheets - expected value is cost of timesheet
product lines - expected value is always 0
stock usage - expected value is cost of stock usage per subject to FIFO etc
purchase line - expected value is PO line quantity x PO line cost x PO exchange rate / for lines that do match a product line
unforecast purchase (forecast) - expected value is always 0 / forecast purchase lines that do not match a product line
unforecast purchase (actual) - PO line quantity x PO line cost x PO exchange rate / for lines that do not match a product line
ACTUALQTYproduct: numerical value
task: hour/minutes
line item actual quantity
task lines - expected value is always 0
timesheets - expected value is length of timesheet
product lines - expected value is always 0
stock usage - expected value is always usage qty
purchase line - expected value is PO line qty / for lines that do match a product line
unforecast purchase (forecast) - expected value is always 0 / forecast purchase lines that do not match a product line
unforecast purchase (actual) - expected value is PO line qty / for lines that do not match a product line

ACTUALVALUEdollar valueline item actual quantity
task lines - expected value is sum of invoice task line amount x invoice exchange rate
timesheets - expected value is always 0
product lines - expected value is sum of invoice product line amount x invoice exchange rate
stock usage - expected value is always 0
purchase line - expected value is sum of invoice purchase line amount x invoice exchange rate / for lines that do match a product line
unforecast purchase (forecast) - expected value is always 0 / forecast purchase lines that do not match a product line
unforecast purchase (actual) - expected value is sum of invoice purchase line amount x invoice exchange rate / for lines that do not match a product line
BILLABLEyes/no
line item billable status
BILLINGCLIENTtextbilling client name
CLIENTtextclient name
COMPLETEDDATEDD/MM/YYYYproject completed date
COSTVARIANCEdollar valueline item cost variance between forecast/actual cost
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject due day
DAYOFWEEKday nameproject due day name
DESCRIPTIONtextline item description
DISCOUNTdollar valueline item discount
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueline item forecast cost
FORECASTQTYproduct: numerical value
task: hour/minutes
line item forecast quantity
FORECASTVALUEdollar valueline item forecast value
LINETYPEtextline item type (e.g. task, product)
MONTHnumerical month/month nameproject due month
NAMEtextline item name
PHASEtextline item phase
PROJECTDESCRIPTIONproject description fieldproject description
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
QTRmonth-monthproject due quarter
QTYVARIANCEproduct: numerical value
task: hour/minutes
line item forecast/actual quantity variance
SKUtextline item SKU (products only)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
VALUEVARIANCEdollar valueline item forecast/actual value variance
YEARnumerical valueproject due date year

Project Forecast VS Actual (Grouped)

Overview
This report details forecast vs actual information per line for projects completed or due for completion within the selected period. 

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valueline item actual cost
task lines - expected value if using Tanda integration then use Tanda cost otherwise fall back to timesheet cost
product lines (forecastedPurchaseLine inclusive) - expected value is always sum of PO line cost + any stock usage cost subject to FIFO if product id matches
unforecast purchase - expected value is always unforecast purchase line total cost
ACTUALQTYnumerical valuetask lines - expected value is always sum of timesheet length
product lines (forecastedPurchaseLine inclusive) - expected value is always sum of PO line quantity + sum of stock usage quantities on the project that match the product ID
unforecast purchase - expected value is always unforecast purchase line item quantity / for PO lines that cannot be found by their ID, SKU or name 
ACTUALVALUEdollar valuetask lines - expected value is always sum of the project invoice task line amount x invoice exchange rate
product lines (forecastedPurchaseLine inclusive) - expected value is always sum of the project product invoice line value x invoice exchange rate + the sum of matching project PO line item value x invoice exchange rate
unforecast purchase - expected value is always sum of invoice purchase line amount x invoice exchange rate / for PO lines that cannot be found by their ID, SKU or name
BILLABLEyes/no
line item billable status
BILLINGCLIENTtextbilling client name
CLIENTtextclient name
COMPLETEDDATEDD/MM/YYYYproject completed date
COSTVARIANCEdollar valueline item cost variance between forecast/actual cost
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject due day
DAYOFWEEKtextproject due day name
DESCRIPTIONtextline item description
DISCOUNTdollar valueline item discount
DUEDATEDD/MM/YYYYproject due date
FORECASTCOSTdollar valueline item forecast cost
FORECASTQTYnumerical valueline item forecast quantity
FORECASTVALUEdollar valueline item forecast value
LINETYPEtextline item type (e.g. task, product)
MONTHnumerical month/month nameproject due month
NAMEtextline item name
PHASEtextline item phase
PROJECTDESCRIPTIONtextproject description
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
QTRmonth-monthproject due quarter
QTYVARIANCEnumerical valueline item forecast/actual quantity variance
SKUtextline item SKU (products only)
STARTDATEDD/MM/YYYYproject start date
STATUStextproject status
VALUEVARIANCEdollar valueline item forecast/actual value variance
YEARnumerical valueproject due date year

Project Activity Lines Report

Overview
This report brings all project-related activity within a period into a single table, including invoices, purchases, timesheets, and stock usage, broken down into cost or revenue line items.

Fields

FieldNotes / Expected ValuesDescription
ASSETtextproject asset
BILLINGCLIENTtextbilling client name
BILLINGCLIENTREGIONtextbilling client region
CLIENTtextclient name
CLIENTCODEtextproject client code
CLIENTREGIONtextproject client region
COSTdollar valueline item cost
DATEDD/MM/YYYYactivity date (e.g. usage)
DAYnumerical valueactivity day (e.g. usage)
DAYOFWEEKtextactivity day name (e.g. usage)
DESCRIPTIONtextline item description (e.g. usage)
ITEMtextline item name
MONTHnumerical month/month nameactivity month (e.g. usage)
PHASEtextline item phase
PRODUCTCATEGORYtextproduct details category
PROFITdollar valueline item profit
PROJECTproject number - project nameproject number - project name
PROJECTDESCRIPTIONtextproject description
PROJECTGROUPtextproject group name
PROJECTMANAGERtextproject manager name
PROJECTNAMEtextproject name
PROJECTNOnumerical valueproject number
PROJECTSTATUStextproject status
QTRmonth-monthactivity quarter (e.g. usage)
QUANTITYnumerical valueactivity quantity (e.g. usage)
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
REVENUEdollar valueactivity revenue (e.g. usage)
SOURCEtextsource of line data (e.g. purchase, stock usage, invoice, etc)
SOURCENOnumerical valuesource number (e.g. line items purchase order number, invoice number)
SOURCENODATEDD/MM/YYYYsource number date (e.g. invoice date)
SUPPLIERtextif line is linked to a purchase, display purchase supplier
UNITCOSTdollar valueline item unit cost
UNITPRICEdollar valueline item unit price
YEARnumerical valueline item usage year

Production Job Forecast VS Actual

Overview
This report details forecast vs actual information per production job line, including unforecast purchase lines and matching adhoc lines by SKU.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valueline item actual cost
task lines - expected value is always 0
timesheets - expected value is cost of timesheet
product lines - expected value is always 0
stock usage - expected value is cost of stock usage per subject to FIFO etc
purchase line - expected value is PO line quantity x PO line cost x PO exchange rate / for lines that do match a product line
unforecast purchase (forecast) - expected value is always 0 / forecast purchase lines that do not match a product line
unforecast purchase (actual) - If PO is received AND/OR has supplier invoice number applied - expected value is received quantity x invoice price rounded up to 2 decimal places
If PO is not received - expected value is line item buy price x order quantity rounded up to 2 decimal places
production job output line - expected value is unit cost x quantity from the production job inputs 
ACTUALQTYnumerical valueline item actual quantity
task lines - expected value is always 0
timesheets - expected value is length of timesheet
product lines - expected value is always 0
stock usage - expected value is always usage qty
purchase line - expected value is PO line qty / for lines that do match a product line
unforecast purchase (forecast) - expected value is always 0 / forecast purchase lines that do not match a product line
unforecast purchase (actual) - expected value is PO line qty / for lines that do not match a product line
production job output line - expected value is the actual quantity of the output line
COMPLETEDDATEDD/MM/YYYYproduction job completed date
COSTVARIANCEdollar valueline item cost variance
DATEDD/MM/YYYYproduction job due date
DAYnumerical valueproduction job due date day
DAYOFWEEKtextproduction job due day name
DESCRIPTIONtextline item description
DUEDATEYYYY/MM/DDproduction job due date
FORECASTCOSTdollar valueline item forecast cost
FORECASTQTYnumerical valueline item forecast quantity
LINETYPEtextline item type (e.g. task, product)
MONTHnumerical month/month nameproduction job due date month
NAMEtextline item name
PHASEtextline item phase
PRODJOBDESCRIPTIONtextproduction job description
PRODJOBNAMEtextproduction job name
PRODJOBNOnumerical valueproduction job number
PROJECTMANAGERtextproduction job manager
QTRmonth-monthproduction job due date quarter
QTYVARIANCEnumerical valueline item quantity variance
SKUtextline item SKU
STARTDATEDD/MM/YYYYproduction job start date
STATUStextproduction job status
SUPPLIERtextPO line supplier
YEARnumerical valueproduction job due year



Production Job Forecast VS Actual (Grouped)

Overview
Grouped version consolidates forecast and actuals together per production job line item with adhoc lines matched by SKU.

Fields

FieldNotes / Expected ValuesDescription
ACTUALCOSTdollar valueline item actual cost
task lines - expected value if using Tanda integration then use Tanda cost otherwise fall back to timesheet cost
product lines (forecastedPurchaseLine inclusive) - expected value is always sum of PO line cost + any stock usage cost subject to FIFO if product id matches
unforecast purchase - expected value is always unforecast purchase line total cost
production job output line - expected value is the output line unit cost x quantity produced
ACTUALQTYnumerical valuetask lines - expected value is always sum of timesheet length
product lines (forecastedPurchaseLine inclusive) - expected value is always sum of PO line quantity + sum of stock usage quantities on the project that match the product ID
unforecast purchase - expected value is always unforecast purchase line item quantity / for PO lines that cannot be found by their ID, SKU or name
production job output line - expected value is actual quantity of the output
COMPLETEDDATEDD/MM/YYYYproduction job completed date
COSTVARIANCEdollar valueline item cost variance
DATEDD/MM/YYYYproduction job due date
DAYnumerical valueproduction job due date day
DAYOFWEEKday nameproduction job due day name
DESCRIPTIONtextline item description
DUEDATEDD/MM/YYYYproduction job due date
FORECASTCOSTdollar valueline item forecast cost
FORECASTQTYnumerical valueline item forecast quantity
LINETYPEtextline item type (e.g. task, product)
MONTHnumerical day/month abbreviatedproduction job due date month
NAMEtextline item name
PHASEtextline item phase
PRODJOBDESCRIPTIONtextproduction job description
PRODJOBNAMEtextproduction job name
PRODJOBNOnumerical valueproduction job number
PROJECTMANAGERtextproduction job manager
QTRmonth-monthproduction job due date quarter
QTYVARIANCEnumerical valueline item quantity variance
SKUtextline item SKU
STARTDATEDD/MM/YYYYproduction job start date
STATUStextproduction job status
SUPPLIERtextPO line supplier
YEARnumerical valueproduction job due year



Recurring Projects by End Date Pivot

Overview
This pivot table report shows all recurring project lines ending in the selected period. Perfect for monitoring scheduled recurring work.

Fields

FieldNotes / Expected ValuesDescription
CLIENTclient name fieldrecurring project client
CLIENTCODEtextproject client code
DATEDD/MM/YYYYrecurring project end date
DAYnumerical valuerecurring project end date day
DAYOFWEEKday namerecurring project end date day name
DESCRIPTIONtextline item description
FREQUENCYnumber of daysrecurring project frequency
INVOICEDATEDD/MM/YYYYline item invoice date
INVOICENOnumerical valueline item invoice number
LINECOSTdollar valueline item cost
LINETYPEtextline item type (e.g. task, product)
LINEVALUEdollar valueline item value
MONTHnumerical month/month namerecurring project end date month
NAMEtextline item name
NEXTDATEDD/MM/YYYYrecurring project next recurring date
QTRmonth-monthrecurring project end date quarter
QUANTITYnumerical valueline item forecast quantity
RECURRINGPROJECTDESCRIPTIONtextrecurring project description
SELLPRICEdollar valueline item sell price
STAFFtexttask line assigned staff
STARTDATEDD/MM/YYYYrecurring project start date
STATUStextrecurring project status
TEAMtexttask line assigned team
TEMPLATEtextrecurring project assigned template
UNITCOSTdollar valueline item unit cost
YEARnumerical valuerecurring project due year

Recurring Projects and Invoiced Amount In Period

Report Overview
This report shows only projects due for completion within the selected date range. Basically, it’s a handy way to check which recurring projects wrapped up (or are due) in that time window and how much was invoiced compared to forecasted — great for spotting trends and checking billing accuracy over time.

FieldNotes/Expected ValuesDescription
BILLINGCLIENTtextproject billing client
CLIENTPURCHASEORDERtextproject 'client PO'
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject due day
DAYOFWEEKtextproject due day name
FORECASTVALUEINPERIODdollar valueforecast project value in period (e.g. if report is run for 2 months and there is 2 1 month projects in that time - result is for both projects)
INVOICEDINPERIODforecast project value in period (e.g. if report is run for 2 months and there is 2 1 month projects in that time - result is for both projects)
INVOICENOnumerical valueproject invoice number
MONTHnumerical month/month nameproject due month number and month name
NEXTDATEDD/MM/YYYYnext project start date
NUMBERINPERIOD
project number in period (e.g. if report is run for 2 months and there is 2 1 month projects in that time - result is going to be 2)
PROJECTFORECASTVALUEdollar valueproject forecast value
QTRmonth-monthproject due quarter
REMAININGVALUEdollar valueremaining value to invoice
REMAININGVALUEINPERIODdollar valueremaining non-invoiced value in period (e.g. if report is run for 2 months and there is 2 1 month projects in that time - result is for both projects)
STARTDATEDD/MM/YYYYproject start date
YEARnumerical valueproject start year
FORECASTVALUE (sum)dollar valueproject total forecast value
INVOICED (sum)dollar valueproject total invoiced
CLIENTtextproject client
TEMPLATEtextproject template name
FREQUENCYdays/months/yearsrecurring project frequency
PROJECTnumerical valueproject number



Recurring Projects Forecast vs Actual Revenue in Period Summary Report

Report Overview
This one’s a big-picture summary showing the forecasted vs actual revenue for each recurring project across the whole recurrence period. It doesn’t just show what’s already billed — it also includes forecasted revenue for jobs that haven’t even been created yet. Super useful if you want a top-down look at how recurring projects are tracking against expectations.

FieldNotes/Expected ValuesDescription
ASSETtextproject asset
BILLINGCLIENTtextproject billing client
CLIENTPURCHASEORDERtextproject 'Client PO'
CONTACTtextproject client contact
DATEDD/MM/YYYYproject due date
DAYnumerical valueproject due day
DAYOFWEEKtextproject due day name
DESCRIPTIONtextproject description
MONTHnumerical month/month nameproject due month number and month name
NEXTDATEDD/MM/YYYYnext project start date
PROJECTGROUPtextproject group name
QTRmonth-monthproject due quarter
TEMPLATEtextproject template name
YEARnumerical valueproject end year
PROJECTFORECASTREVENUE (sum)dollar valueproject total forecast revenue
PROJECTACTUALREVENUE (sum)dollar valueproject total actual revenue
TEMPLATEFORECASTREVENUE (sum)dollar valueproject template forecast total revenue
FORECASTANDACTUALREVENUEFORPERIOD (sum)dollar valueproject total forecast and actual revenue in period
FORECASTFORPERIOD (sum)dollar valueproject total forecast value in period
STATUStextproject status
CLIENTtextproject client name
NAMEtextproject name

Project Template Summaries Pivot Report

Report Overview
This report gives you a bird’s-eye view of project templates — think of it as a snapshot of forecasted costs, revenue, and profit across your different template setups. Perfect for comparing how your templates perform overall.

FieldNotes/Expected ValuesDescription
GPdollar valueproject gross profit
PHASEStextlist of project phases
STAFFtexttask assigned staff name
TEAMStexttask assigned team name
FORECASTCOST (sum)dollar valuetemplate forecast cost
FORECASTREVENUE (sum)dollar valuetemplate forecast revenue
FORECASTPROFIT (sum)dollar valuetemplate forecast profit
TYPEtexttemplate type (e.g. production job, project)
NAMEtexttemplate name
DESCRIPTIONtexttemplate description

Project Template Lines Pivot Report

Report Overview
This report dives into the line items that make up your project templates. It’s good for checking how quantities, rates, and costs stack up per template, phase, or staff member. Handy if you’re trying to see which parts of a template chew up the most resources or deliver the best return.

FieldNotes/Expected ValuesDescription
BILLABLETrue/False/N/ALine billable status
DESCRIPTIONtextline item description
PHASEtextline item phase
STAFFtexttask assigned staff
SUPPLIERtextpurchase template supplier
TEAMStexttask assigned team
TEMPLATEDESCRIPTONtexttemplate description
QUANTITY (sum)numerical valueline item quantity
UNITCOST (sum)dollar valueline item unit cost
UNITRATE (sum)dollar valueline item unit value
TEMPLATETYPEtexttemplate type (e.g. production job, project)
TEMPLATENAMEtexttemplate name
LINETYPEtextline item type (e.g. task, product)
SKUtextproduct SKU
NAMEtextline item name

Project Notes Pivot Report

Report Overview
This one’s straightforward — it shows project notes that were created within the selected date range. It’s great for checking activity, tracking communication, or confirming that important details are logged on projects as expected.

FieldNotes/Expected ValuesDescription
CLIENTtextclient name
DATEDD/MM/YYYYnote creation date
DAYnumerical valuetransaction due day
DAYOFWEEKtexttransaction due day name
ENDDATEDD/MM/YYYYtransaction due date
MONTHnumerical month/month nametransaction due month
PROJECTMANAGERtexttransaction manager
QTRmonth-month transaction due date quarter
SOURCEDESCIPTIONtexttransaction description
SOURCENAMEtext/numerical valuetransaction name/project number
STARTDATEDD/MM/YYYYtransaction start date
YEARnumerical valuetransaction due year
SOURCETYPEtexttransaction type (production job/project)
STATUStexttransaction status
SOURCENUMBERnumerical valuetransaction number
NOTEtexttransaction note content

Estimated Billing by Line Item

Report Overview
This report estimates billing amounts by individual line items within projects. It’s particularly useful for seeing where revenue is expected to land — including what’s already billed versus what’s still forecasted. Think of it as a forward-looking billing forecast by project component.

FieldNotes/Expected ValuesDescription
ACTUALQTYnumerical valuetransaction actual line item quantity
CLIENTtexttransaction client
COSTdollar valueline item cost
DESCRIPTIONtextline item description
DUEDATEDD/MM/YYYYtransaction due date
FORECASTQTYnumerical valuetransaction forecast line item quantity
ITEMtextline item SKU / name
LINETYPEtextline item type (e.g. task, product)
NAMEtextline item name
PHASEtextline item phase
PROJECTGROUPtextproject group name
PROJECTNAMEtextproject name
REPORTINGCATEGORYOPTION1textXero tracking category tied to transaction (if enabled and imported from Xero)
REPORTINGCATEGORYOPTION2textXero tracking category tied to transaction (if enabled and imported from Xero)
SKUnumerical valueproduct SKU
STARTDATEDD/MM/YYYYproject start date
ALREADYBILLED (sum)dollar valuetransaction total line item value already billed
BILLABLEVALUE (sum)dollar valuetransaction total line item billable value
ESTIMATEDBILLING (sum)dollar valuetransaction total line item value remaining to be billed
PROJECTSTATUStextproject status
PROJECTMANAGERtextproject manager name
PROJECTNOnumerical valueproject number


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article